The Tennessee Valley Authority (TVA) is working on converting the Cumberland Fossil Plant into the new Cumberland Natural Gas Plant, southwest of Clarksville. The $2.1 billion natural gas plant is set to be completed in late 2026 and will receive natural gas from a 32-mile, 30-inch gas pipeline. As part of the transition from coal-fired units, TVA plans to decommission one of the coal units in 2020 and the other in 2028. The new gas-fired plant will supply 1,450 megawatts of power, capable of powering 840,000 homes, but TVA also plans to integrate 10,000 megawatt of solar onto the system by 2035.

Solar Dominates US Energy Capacity Growth
The Federal Energy Regulatory Commission (FERC) has published data showing that solar accounted for over 75% of US electrical generating