Trade group Advanced Energy United has filed testimony against Dominion Energy’s Virginia utility for artificially limiting the amount of solar, wind and storage that could be added each year in the resource plan submitted to state regulators. The trade group said that Dominion did not develop a least-cost resource plan compliant with the Virginia Clean Economy Act (VCEA). Dominion limited solar capacity additions to 900 MW per year through 2038, but in its 2020 resource plan, it selected 1,440 MW of utility-scale solar for several years within the planning period. The Sierra Club also challenged Dominion’s resource planning process, suggesting that state regulators require Dominion to revise its resource plan by lifting or easing the build limits it placed on solar PV and battery storage.

Solar Dominates US Energy Capacity Growth
The Federal Energy Regulatory Commission (FERC) has published data showing that solar accounted for over 75% of US electrical generating