PJM Interconnection, the electric grid operator for 13 Mid-Atlantic and Midwest states and the District of Columbia, has announced its capacity price for the upcoming service year at $329.17 per megawatt-day, marking a 21.9 percent increase from the record-high price of $269.92 this year. This could result in an increase of about 1.5 to 5 percent in customers’ bills depending on their area. The capacity price was set after a complaint from Pennsylvania Gov. Josh Shapiro alleging PJM was slow to put projects into the grid, leading to a potential cost of over $20 billion in charges in the next two years. Total capacity costs for PJM consumers in 2025 capacity auction surged to $16.1 billion, up from $14.7 billion in the 2024 auction.

Solar Dominates US Energy Capacity Growth
The Federal Energy Regulatory Commission (FERC) has published data showing that solar accounted for over 75% of US electrical generating