The Michigan Public Service Commission (MPSC) has issued a final order regarding the contract with a data center requesting 1.4 gigawatt (GW) of electricity, which would increase the utility’s load by 25%. The MPSC also responded to a petition by another major utility, Consumers Energy, seeking changes to the terms and conditions for data centers. UCS intervened in the case with a coalition of clean energy organizations suggesting ways that data centers could support Michigan’s efforts to provide reliable, clean, and affordable electricity. The commission agreed with these recommendations but did not take up clean energy requirements or interconnection reform. The final order on the case was issued on November 6, with additional reporting requirements based on these recommendations.

Solar Dominates US Energy Capacity Growth
The Federal Energy Regulatory Commission (FERC) has published data showing that solar accounted for over 75% of US electrical generating