Legislators Demand Accountability from California Utilities

Eighteen California legislators have written to the California Public Utilities Commission (CPUC) asking them to hold Pacific Gas & Electric and Southern California Edison accountable for repeatedly missing state-mandated timelines to interconnect solar and storage. The legislators argue that these delays lead to higher rates for customers who pay high rates to the utility rather than savings. They also point out that utilities miss state-imposed timelines up to 73% of the time. The California Solar & Storage Association has filed a complaint with the CPUC alleging that PG&E and SCE have consistently failed to meet the timeline requirements of Rule 21 and have not shown a pattern of improvement towards these requirements. The CPUC has not yet decided to enforce these rules.