Flatiron Energy secured approximately $540 million in financing for the Taft battery project in Uxbridge, Mass. The project, set to be the largest in Massachusetts, is expected to be 200 MW, 800 MWh and will store enough energy to supply about 40,000 households for one month. The site is located along a transmission line corridor on land previously used as an industrial development. The Taft project is set to create up to 30 jobs for local skilled workers. The financing commitments include construction and bridge loan facilities, term loans, letter of credit facilities, a preferred equity commitment, and a tax credit transfer commitment.

Solar Dominates US Energy Capacity Growth
The Federal Energy Regulatory Commission (FERC) has published data showing that solar accounted for over 75% of US electrical generating