A federal court is skeptical that Maine failed to provide enough information when it denied a water quality permit for a hydropower project. The issue involves a permit held by Brookfield White Pine Hydro to operate the Shawmut Hydroelectric Project on the lower Kennebec River, which is undergoing relicensing before the Federal Energy Regulatory Commission. The project requires a certificate from the state before FERC can issue a new license. The Maine Department of Environmental Protection denied a certificate in October 2022. Matthew Warner, an attorney for the company, argued that the state had not provided sufficient details about its decision and left Brookfield without an idea of what to do to comply.