California Energy Commission (CEC) has approved a 4.6GWh solar-storage project, DCEP, which will be built across 9,500 acres of land in Western Fresno County. The project will feature a 1.15GW/4.6 GWh BESS paired with a solar PV farm. Initial plans included up to 800MW of electrolyser capacity, but this project was later dropped by developer Intersect Power. The California Energy Commission hailed the project as the largest BESS in the world, but construction is likely to take up to three years. Other independent power producers (IPPs) are also constructing their own mega BESS projects within California. Despite opposition, some California lawmakers have attempted to pass legislation relinquishing the CEC’s authority over BESS.

Solar Dominates US Energy Capacity Growth
The Federal Energy Regulatory Commission (FERC) has published data showing that solar accounted for over 75% of US electrical generating